Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revision Previous revision
Next revision
Previous revision
projects:maint-6-18-2016 [2016/06/17 14:48]
Hans [Scheduled Preparation Week of 6/13]
projects:maint-6-18-2016 [2016/06/29 11:58] (current)
Hans
Line 1: Line 1:
-====== ICS Maintenance June 18, 2006 ======+====== ICS Maintenance June 18, 2016 ======
  
 In order to accomodate a 12 hour facilities shutdown on June 19, 2006,  ICS Computing Support will begin shutting down non-critical ICS infrastructure in the ICS Datacenter at 5pm on June 17, 2016 and performing general maintenance throughout the day on June 18th, 2016. In order to accomodate a 12 hour facilities shutdown on June 19, 2006,  ICS Computing Support will begin shutting down non-critical ICS infrastructure in the ICS Datacenter at 5pm on June 17, 2016 and performing general maintenance throughout the day on June 18th, 2016.
Line 79: Line 79:
 | 6/18 9:15am | [[group:​support:​services:​gitlab|Gitlab]] shutdown and directory migration | | 6/18 9:15am | [[group:​support:​services:​gitlab|Gitlab]] shutdown and directory migration |
 | 6/17 9:30am | Move ICS Shared to [[hardware:​storage:​cybertron|Cybertron]]| | 6/17 9:30am | Move ICS Shared to [[hardware:​storage:​cybertron|Cybertron]]|
-| 6/18 10am| (12hours) Begin Rolling restart of critical infrastructure hosts|+| 6/18 10am| (36 hours) Begin Rolling restart of critical infrastructure hosts|
 | 6/18 10am| ICS MySQL Server Maintenance| | 6/18 10am| ICS MySQL Server Maintenance|
 | 6/18 10:30am| Update Cybertron LDAP Configuration| | 6/18 10:30am| Update Cybertron LDAP Configuration|
 | 6/18 11am| Upgrade bunker to CentOS7 operating system with ZFS on Linux| | 6/18 11am| Upgrade bunker to CentOS7 operating system with ZFS on Linux|
 | 6/18 10pm | Shutdown non-critical hosts and infrastructure in the ICS DC| | 6/18 10pm | Shutdown non-critical hosts and infrastructure in the ICS DC|
 +| 6/18 2pm | IGB 10Gb/s Uplink Activation|
 | 6/19 5am| We anticipate loss of commercial power and cooling to the data center| | 6/19 5am| We anticipate loss of commercial power and cooling to the data center|
 | 6/19 5pm| We anticipate that power will be restored to the ICS DC.  Some hosts will power on | | 6/19 5pm| We anticipate that power will be restored to the ICS DC.  Some hosts will power on |
Line 89: Line 90:
 | 6/19 10pm| #59377: Fwd: Power on hosts for BIC | | 6/19 10pm| #59377: Fwd: Power on hosts for BIC |
 | 6/20 8am| Restore Nagios notifications. ​ Check Observium and Ganglia Reports| ​ | 6/20 8am| Restore Nagios notifications. ​ Check Observium and Ganglia Reports| ​
 +| 6/20 9am| Rebuild SGE Queues| ​
  
  
projects/maint-6-18-2016.1466200120.txt.gz ยท Last modified: 2016/06/17 14:48 by Hans