projects:maint-6-18-2016 [2016/06/17 14:48] Hans [Scheduled Preparation Week of 6/13] |
projects:maint-6-18-2016 [2016/06/29 11:58] (current) Hans |
||
---|---|---|---|
Line 1: | Line 1: | ||
- | ====== ICS Maintenance June 18, 2006 ====== | + | ====== ICS Maintenance June 18, 2016 ====== |
In order to accomodate a 12 hour facilities shutdown on June 19, 2006, ICS Computing Support will begin shutting down non-critical ICS infrastructure in the ICS Datacenter at 5pm on June 17, 2016 and performing general maintenance throughout the day on June 18th, 2016. | In order to accomodate a 12 hour facilities shutdown on June 19, 2006, ICS Computing Support will begin shutting down non-critical ICS infrastructure in the ICS Datacenter at 5pm on June 17, 2016 and performing general maintenance throughout the day on June 18th, 2016. | ||
Line 79: | Line 79: | ||
| 6/18 9:15am | [[group:support:services:gitlab|Gitlab]] shutdown and directory migration | | | 6/18 9:15am | [[group:support:services:gitlab|Gitlab]] shutdown and directory migration | | ||
| 6/17 9:30am | Move ICS Shared to [[hardware:storage:cybertron|Cybertron]]| | | 6/17 9:30am | Move ICS Shared to [[hardware:storage:cybertron|Cybertron]]| | ||
- | | 6/18 10am| (12hours) Begin Rolling restart of critical infrastructure hosts| | + | | 6/18 10am| (36 hours) Begin Rolling restart of critical infrastructure hosts| |
| 6/18 10am| ICS MySQL Server Maintenance| | | 6/18 10am| ICS MySQL Server Maintenance| | ||
| 6/18 10:30am| Update Cybertron LDAP Configuration| | | 6/18 10:30am| Update Cybertron LDAP Configuration| | ||
| 6/18 11am| Upgrade bunker to CentOS7 operating system with ZFS on Linux| | | 6/18 11am| Upgrade bunker to CentOS7 operating system with ZFS on Linux| | ||
| 6/18 10pm | Shutdown non-critical hosts and infrastructure in the ICS DC| | | 6/18 10pm | Shutdown non-critical hosts and infrastructure in the ICS DC| | ||
+ | | 6/18 2pm | IGB 10Gb/s Uplink Activation| | ||
| 6/19 5am| We anticipate loss of commercial power and cooling to the data center| | | 6/19 5am| We anticipate loss of commercial power and cooling to the data center| | ||
| 6/19 5pm| We anticipate that power will be restored to the ICS DC. Some hosts will power on | | | 6/19 5pm| We anticipate that power will be restored to the ICS DC. Some hosts will power on | | ||
Line 89: | Line 90: | ||
| 6/19 10pm| #59377: Fwd: Power on hosts for BIC | | | 6/19 10pm| #59377: Fwd: Power on hosts for BIC | | ||
| 6/20 8am| Restore Nagios notifications. Check Observium and Ganglia Reports| | | 6/20 8am| Restore Nagios notifications. Check Observium and Ganglia Reports| | ||
+ | | 6/20 9am| Rebuild SGE Queues| | ||