This is an old revision of the document!
Table of Contents
ICS Maintenance June 18, 2006
In order to accomodate a 12 hour facilities shutdown on June 18, 2006, ICS Computing Support will begin shutting down non-critical ICS infrastructure in the ICS Datacenter at 5pm on June 17, 2016.
Facilities's Message
Facilities High Voltage Team has been performing preventative maintenance on many of the campus building transformers, switchgear, and breakers. While performing maintenance we have been able to identify and repair many equipment deficiencies and reduce the possibility of electrical failures and outages.
Facilities High Voltage Team has scheduled preventative maintenance on Computer Science T-18 & T-19 transformers and switchgear for Saturday, June 18th, 2016, from 5:00am-5:00pm
In order to perform this maintenance it will require a 12-hour electrical shutdown to the entire building. The only power will be emergency power.
Effects on ICS
ICS Co-Maintenance
ICS will be taking this opportunity to perform maintenance on multiple systems that would individually cause significant disruption for users.
Critical Infrastructure
Effects on Critical infrastructure will be not be affected bavailable during this period. That infrastructure includes:
- ICS Home Page: http://www.ics.uci.edu
- ICS Email Systems
- ICS Home Directory (qualified with exceptions)
- ICS Samba Service (IGB Samba will be unavailable)
- ICS Samba Service
- Many ICS hosted websites (contact helpdesk to see if yours will be available).
Plan on brief outages on several ICS systems during the day. A more specific schedule will be provided later. These items are required to implement network redundancy inside the data center and perform maintenance on systems:
Planned Maintenance
Summary
- ICS NetApp Storage Outaages: Several service interuptions are expected to setup network switch redundancy.
- ICS shared space: Move /net/tron/support0_tainer_sata/shared/ to net/cybertron/vol2/ics_shared
- SGE: Central Spool data relocation
- Subversion data relocation
- Gitlab data relocation
- Complete Data Center Reboot
- Move MySQL
- Move ugrad accounts
- CentOS and Ubuntu OS Patches and Updates
- New UPS installation
- Bunker CentOS7 Upgrade
Gitlab Data Relocation
Copy file Update /etc/auto.gitlab
OS Patches and Updates
Begging on Monday morning, June 10th, we will be running updates on all CentOS and Ubnunt Linux clients. Beginning at 9pm, systems that have been updated will be shutdown.
Storage Shutdown
The following NFS servers will be unavailable beginning at 9pm on Friday the 17th.
- bunker.ics.uci.edu
- coachz.ics.uci.edu
- gaia.ics.uci.edu
- gigantor.ics.uci.edu
- kraken.ics.uci.edu
- nerve.ics.uci.edu
Scheduled Preparation Week of 6/13
Date Time | Description |
6/13 All Day | Begin performing yum update on all non-infrastructure CentOS5 hosts |
6/14 All Day | Begin performing yum update on all non-infrastructure CentOS6 hosts |
6/15 All Day | Begin performing yum update on all non-infrastructure CentOS7 hosts |
6/16 All Day | Begin performing apt-get update on all Ubuntu 14.04 hosts |
6/17 5pm | Undergraduate Home Directory Move |
6/17 9pm | SGEsge Shutdown and SGE Spool migration to Cybertron |
6/17 9pm | Gitlab shutdown and directory migration |
6/17 10pm | Move ICS Shared to Cybertron |
6/17 10pm | Move ICS Shared Shutdown |
of 6/13