====== 2018 Fall Quarter Maintenance Schedule ====== ===Openlab Cluster Update === *** Downtime Notice *** * SYSTEM: [[hardware:cluster:openlab|openlab]] systems * DATE: 12/20/2018 * START TIME: 0800 * DURATION: 8 hours ==AFFECTS== All [[hardware:cluster:openlab|openlab]] hosts will be updated and rebooted to apply the latest operating system and security patches. (Please note this is an estimate; systems may be up sonner later than expected, due to unforeseeable circumstances.) === Mimir Cluster Relocation === *** Downtime Notice *** * SYSTEM: mimir systems * DATE: 10/16/2018 * START TIME: 0930 * DURATION: 2 hours ==AFFECTS== The mimir hosts will be relocated to another cabinet in the ICS Data Center. (Please note this is an estimate; systems may be up sooneror later than expected, due to unforeseeable circumstances.) === Datalab Cluster Relocation === *** Downtime Notice *** * SYSTEM: datalab systems * DATE: 10/17/2018 * START TIME: 0930 * DURATION: 2 hours ==AFFECTS== The datalab hosts will be relocated to another cabinet in the ICS Data Center. (Please note this is an estimate; systems may be up sooneror later than expected, due to unforeseeable circumstances.)