projects:maint-summer-2018 [2018/09/05 08:13]
Hans [VirtualBox Upgrade]
projects:maint-summer-2018 [2018/09/14 10:50] (current)
hans [Summer Quarter Maintenance]
Line 5: Line 5:
 [[https://​calendar.google.com/​calendar/​embed?​src=ics.uci.edu_rbt2q6kmhapqm4bjaet1j48h00@group.calendar.google.com&​ctz=America/​Los_Angeles|ICS Computing Support Maintenance Calendar]] [[https://​calendar.google.com/​calendar/​embed?​src=ics.uci.edu_rbt2q6kmhapqm4bjaet1j48h00@group.calendar.google.com&​ctz=America/​Los_Angeles|ICS Computing Support Maintenance Calendar]]
  
-====Fall Quarter Maintenance====+====Summer ​Quarter Maintenance====
  
-Fall quarter Maintenance has been schedule for 9/​17/​2018. ​  ​Please check the [[projects:​maint-summer-2018|Summer Maint. website]] for updates. ​ Send email ot helpdesk@ics.uci.edu to have maintenance rescheduled.+Fall quarter Maintenance has been schedule for 9/​17/​2018. ​  ​Please check the [[projects:​maint-summer-2018|Summer Maint. website]] for updates. ​ Send email to helpdesk@ics.uci.edu to have maintenance rescheduled.
  
   * Date:  9/17/2018   * Date:  9/17/2018
   * Time:  All Day   * Time:  All Day
  
-=== Network Switch ​reboot ​===+=== Network Switch ​Firmware Update and Reboot ​===
  
 **Affected Hosts:** Large number of ICS Hosts **Affected Hosts:** Large number of ICS Hosts
Line 18: Line 18:
 **Reason:** Switch unresponsive to remote logins. **Reason:** Switch unresponsive to remote logins.
  
-**Impact:​**  ​This switch provides ​network ​connections along with a 2nd switch ​for a large number of servers.  ​During ​the rebootthe network ​connection could be disrupted for 30 seconds ​to 1 minute.  ​There is no long anticipated downtime ​with this reboot.+**Impact:​**  ​These switches provide ​network ​connection ​for a large number of servers.  ​As the firmware update occursexcept ​network ​interruptions of up to 1 hour.  ​If you have a server that needs uninterrupted network connection, please email helpdesk@ics.uci.edu ​with the server name and the reason.
  
 === Relocate john-luther to Critical Rack Cluster === === Relocate john-luther to Critical Rack Cluster ===
Line 31: Line 31:
 **Impact**:  ​ **Impact**:  ​
   * gitlab will be unavailable during this period.   * gitlab will be unavailable during this period.
 +
 +=== Pedigree/​Beem systems to new power ===
 +
 +**Affected Hosts**:  ​
 +  * Pedigree cluster
 +  * Beem2 and Beem3
 +
 +**Reason**: ​ Relocating power to 110V to free up power needed for another project.
 +
 +**Impact**: ​ The server will be turned off for about 10-15 minutes while power is rerouted. ​ This will happen after the servers are patched. ​ Rather than a reboot, a brief shutdown will occur instead.
  
 === OS Maintenance === === OS Maintenance ===
Line 75: Line 85:
   * SYSTEM: ​ melvil-dewey-v0.ics.uci.edu   * SYSTEM: ​ melvil-dewey-v0.ics.uci.edu
   * DATE:  September 17, 2018   * DATE:  September 17, 2018
-  * START TIME: 0900+  * START TIME: 0600
   * DURATION: 15 minutes   * DURATION: 15 minutes
  
Line 90: Line 100:
 A restart is required in order to limit the size of the ibtmp1 caching file. A restart is required in order to limit the size of the ibtmp1 caching file.
  
-====VirtualBox 5.2.18 Upgrade====+====VirtualBox 5.2.18 Upgrade ​#​68338: ​====
  
   * SYSTEM: ​ All ICS Systems   * SYSTEM: ​ All ICS Systems
Line 102: Line 112:
  
  
-====Vagrant 2.1.4 Upgrade====+====Vagrant 2.1.4 Upgrade ​#​68338: ​====
  
   * SYSTEM: ​ All ICS Systems   * SYSTEM: ​ All ICS Systems
projects/maint-summer-2018.1536160419.txt.gz · Last modified: 2018/09/05 08:13 by Hans
CC Attribution-Noncommercial-Share Alike 4.0 International