Cybertron Updates

SYSTEM: Cybertron and Unicron Network Appliance Filers

DATE: TBD

START TIME: TBD

DURATION: 2 hour

Reason: Firmware upgrade. Upgrading OnTAP8 to the latest version.

Affects: There is no downtime associated with this work, however a small number of users may experience degraded performance on home or extra directories.

Linux Security Updates

SYSTEM: All Intel Base Linux Hosts

DATE: TBD

START TIME: TBD

DURATION: 2 hour

Reason: Operating system updates are required to patch significant security vulnerability on ALL intel based computers.

Affects: Users will see intermittent downtime on all hosts and related services throughout the maintenance window.

Vagrant Update

SYSTEM: All systems where the Vagrant Package is installed.

DATE: 1/3/2017

START TIME: 1300

DURATION: 2 hour

Reason: Routine update to the vagrant package in order to install compatibility with latest VirtualBox package.

projects/maint-winter-2018.1515015877.txt.gz · Last modified: 2018/01/03 13:44 by Hans
CC Attribution-Noncommercial-Share Alike 4.0 International
Driven by DokuWiki Recent changes RSS feed Valid CSS Valid XHTML 1.0