Summer 2019 Maintenance Schedule
Pedigree cluster relocation
Information Notice
- DATE: 10/3/2019
- START TIME: 0800
- DURATION: 2 hours
AFFECTS
The pedigree cluster will be off briefly to move it to another rack in the server room.
Data Center Power Upgrade Part 2
Information Notice
- DATE: 10/3/2019
- START TIME: 0800
- DURATION: All Day
AFFECTS
Openlab, Benzene, and Helios clusters will be offline during this time.
Data Center Power Upgrade Part 1
Information Notice
- DATE: 09/25/2019
- START TIME: 0800
- DURATION: 1 hour
AFFECTS
The following systems will be offline:
- amazon
- apricot
- ava
- axon-mind
- asterix-1 to 10
- c1ccccc1-2
- c1ccccc1-3
- c1ccccc1-4
- c1ccccc1-32
- c1ccccc1-38 to 55
- cacofonix-1 to 5
- coyote
- gallifrey
- hera
- ieee
- ipubmed1 to 3
- maxwell
- new-c1ccccc1-1
- new-c1ccccc1- 6
- new-c1ccccc1-10
- nimbus
- ochca1
- ochca2
- osgrid
- ronne
- ronne-raid
- ross
- sensorium 1 to 38
- spiritbomb
- unhygienix