Summer 2019 Maintenance Schedule

Pedigree cluster relocation

Information Notice

  • DATE: 10/3/2019
  • START TIME: 0800
  • DURATION: 2 hours

AFFECTS

The pedigree cluster will be off briefly to move it to another rack in the server room.

Data Center Power Upgrade Part 2

Information Notice

  • DATE: 10/3/2019
  • START TIME: 0800
  • DURATION: All Day

AFFECTS

Openlab, Benzene, and Helios clusters will be offline during this time.

Data Center Power Upgrade Part 1

Information Notice

  • DATE: 09/25/2019
  • START TIME: 0800
  • DURATION: 1 hour

AFFECTS

The following systems will be offline:

  • amazon
  • apricot
  • ava
  • axon-mind
  • asterix-1 to 10
  • c1ccccc1-2
  • c1ccccc1-3
  • c1ccccc1-4
  • c1ccccc1-32
  • c1ccccc1-38 to 55
  • cacofonix-1 to 5
  • coyote
  • gallifrey
  • hera
  • ieee
  • ipubmed1 to 3
  • maxwell
  • new-c1ccccc1-1
  • new-c1ccccc1- 6
  • new-c1ccccc1-10
  • nimbus
  • ochca1
  • ochca2
  • osgrid
  • ronne
  • ronne-raid
  • ross
  • sensorium 1 to 38
  • spiritbomb
  • unhygienix
projects/maint-summer-2019.txt · Last modified: 2019/09/30 07:58 by dutran
CC Attribution-Noncommercial-Share Alike 4.0 International
Driven by DokuWiki Recent changes RSS feed Valid CSS Valid XHTML 1.0