projects:maint-summer-2019 [2019/09/26 08:58]
dutran [Data Center Power Upgrade Part 1]
projects:maint-summer-2019 [2019/09/30 07:58] (current)
dutran [Data Center Power Upgrade Part 2]
Line 1: Line 1:
 ====== Summer 2019 Maintenance Schedule ====== ====== Summer 2019 Maintenance Schedule ======
 +
 +==== Pedigree cluster relocation ====
 +
 +** Information Notice **
 +  * DATE: 10/3/2019
 +  * START TIME: 0800
 +  * DURATION: 2 hours
 +
 +** AFFECTS **
 +
 +The pedigree cluster will be off briefly to move it to another rack in the server room.
  
 ==== Data Center Power Upgrade Part 2 ==== ==== Data Center Power Upgrade Part 2 ====
  
 ** Information Notice ** ** Information Notice **
-  * DATE: 10/2/2019+  * DATE: 10/3/2019
   * START TIME: 0800   * START TIME: 0800
   * DURATION: All Day   * DURATION: All Day
projects/maint-summer-2019.1569513521.txt.gz ยท Last modified: 2019/09/26 08:58 by dutran
CC Attribution-Noncommercial-Share Alike 4.0 International
Driven by DokuWiki Recent changes RSS feed Valid CSS Valid XHTML 1.0